Percent complete, duration and activity type.

3 replies [Last post]
xadlim B.
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

Hi guys,

Anybody here has experience of Tunnel Construction? What is the best percent complete type to use? How about the duration type as well as activity type?

Any input is highly appreciated.

 

Thank you.

Replies

Raymund de Laza
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

Unit % must be used if you have the real qty of the Material Resource for every activity. I don't recommend Resource dependent as this will make your duration changing everytime Resources changes.

xadlim B.
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 4 Feb 2012
Posts: 25

Raymund,

If the productivity rate is available, units % type works better? and it should be resource dependent activity type?

Raymund de Laza
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762

xadlim,

If you estimates the Duration of your activity based on linear meter of tunnel time then use the duration % type.

If productivity rate is not available then use Physical % as you estimated the duration based on assumption.

Fixed duration and Units is recommended.

Regards,