In a project how to choice the percent complete type and the duration type

3 replies [Last post]
walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning ;

A small question :

In a project how to choice the percent complete type and the duration type

 

 

thank you

Replies

walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning

Thank you for informations

Jose Frade
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Jose Frade
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Hi Walid.

 

Maybe you can search some explanations in the forum as : http://www.planningplanet.com/forums/primavera-project-planner-p3/418708/understanding-different-type-progress-p6

 

The utilization of the several types may depend on proejct type you have on hands.

 

BR

 

JMFrade