Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS summary activity

6 replies [Last post]
moutaz aldeib
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Hi Planners, Is there a difference between WBS summary activity WBS level? I see they are the same?? Best Moutaz

Replies

moutaz aldeib
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

Thanks Johannes, so this is the only difference. Is it common used this kind of activity or rare?

Best,

Moutaz

Johannes Vandenberg
User offline. Last seen 11 weeks 1 day ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Moutaz

The WBS is a roll-up of all the activities under the WBS.

A WBS summary does the same but you can add resources, costs and expenses. 

Regards Johannes

moutaz aldeib
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None

hi Zoltan,

My question is that: WBS Summary activity is a kind of an activity type that roll up the activities under a WBS element and WBS level is doing the same, is there any difference?

Best

Zoltan Palffy
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

left hand side click on wbs

Safdar Imam
User offline. Last seen 9 years 7 weeks ago. Offline
Joined: 15 Mar 2015
Posts: 2
Groups: None

How to create wbs?

Zoltan Palffy
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

not sure what the question is here. The WBS summary activity is an ACTIVITY TYPE a wbs level can mean that you roll up your activites to a certain wbs level which has noting to do with wbs summary TYPES of activities.