PRIMAVERA Managing Percent Complete

1 reply [Last post]
Charlie Daniels
User offline. Last seen 9 years 26 weeks ago. Offline
Joined: 29 Nov 2013
Posts: 12
Groups: None

Hi 

I have a project which I split into subprojects. 

Example 2 project are activity type projects and are just different disciplines but actually make up one project schedule. 

The 3rd project is a milestone schedule linked to the 2 activity schedules.

I would like to know if there is a way to make the milestone schedule have no weight on the performance % complete calulation for the 2 activity schedules?

 

if I open only the activty programs I get 20% complete, if i open all 3 I get 3% complete.

This does not make complete sense since the milestones don't even role up percent coplete into the wbs like the activity schedules do.

I understand it probably weighs down the progress simply because it adds weight to the schedules, being linked to them.

Is there a way for me to keep this structure, but remove the weighting of the milestones on the activity plans?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you cant roll up percent completes becasue activities can have different percent complete TYPES

this woudl be like compairing apples and oranges

here is a link to my documentation expalinig this 

http://pmsite.com/forums/viewthread/3068/