Summary of Percent Complete

10 replies [Last post]
Emma Seaton
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Does anyone know if it’s possible to display the percent complete of a WBS level on the activity spreadsheet? It shows a summary of OD/RD, dates and float etc., but not %’s. Anyone know the fix, or why it doesn’t if there isn’t one?

I’m refering to Physical % Complete before anyone asks!!

Cheers

Replies

Jorge Taguinod
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Hi Emma,

I’m on my PC now and checked. You may want to use Performance % Complete. :)

That shows up on the WBS. And if you check the definition with Hint Help, I guess it would suit your purposes.

Best,

Jorge
Emma Seaton
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
OK, have now had a look at all the different types of % complete. This confirms that Activity and Physical percentages do not show up at all on the WBS line, but all the rest do. However, the only ones to show anything greater than 0% were Duration % and Duration % of original.

Ugh! Whose Idea was it to have all these different types!!!!!!!
Emma Seaton
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
David

Thanks - I forgot to appreciate what physical percentage was covering.... may try and see if any of the other percentages make a difference...

Legs are overrated anyway ;o)
Emma Seaton
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Steve, how are you?!!! We’re soon to move over to GS House, so I’ll wander on up and say Hi some time!

Thanks for the reply - that makes sense! I’ll try the other myriad of % completes to see if it makes a difference.

:o)
David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
You have entered a minefield!! Luckily with no legs left I can maybe help you. When you record a percent complete against an activity, are you measuring:

a) how much of the work has been done (i.e. resources)
b) how much of the duration has been achieved
c) how much of the monety has been spent
d) how much value has been earned

Jorge Taguinod
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 8 Jul 2003
Posts: 139
Hi Emma,

I think you can do it. I’m not in fron of my Primavera Enterprise (PE) right now but I think you could display NOT physical PCT but ACTIVITY PCT.

That should do it.

Good luck.

Jorge
Steven Oliver
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Emma,

The reason that you will not get a summary of physical % complete, is because you are not comparing like terms.

How would you generate a summary % if your physical quantities refer to manhours, Km of cable and m3 of concrete?


BTW it’s nice to be back in York !
Jose Frade
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Sorry

Can’t advise on that.

I’m sure help will be available pretty soon.

BR
JMFrade
Emma Seaton
User offline. Last seen 10 years 31 weeks ago. Offline
Joined: 16 Sep 2005
Posts: 55
Groups: None
Sorry, should have said I’m using Primavera v5
Jose Frade
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hello Emma

I had it displayed (P3.1) without any trouble.
Simply selecting the Percent complete field.

Can you be more specific ?

BR
JMFrade