History information

1 reply [Last post]
Jaco du Toit
User offline. Last seen 10 years 9 weeks ago. Offline
Joined: 18 Jul 2013
Posts: 8
Groups: None

Good day

I need help. I took over from a previous planner and now they want progress on previous dates.

for example they want early start cost and late start cost for a specific date in the past.

Is there a way in primavera that I can recall that information

 

Thank you in advance

Replies

Shah. HB
User offline. Last seen 20 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Jaco du Toit

 

1.     The first step is check the programme is cost loaded and how progress updates procedure (Weekly / Monthly Progress updates) used for schedule maintenance.

2.     If the programme is cost loaded you can find early and late value distribution in resource assignment directory.

 

 

Cheers

Shahul