Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline budgeted units update

No replies
Jean Desjardins
User offline. Last seen 8 years 9 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Dear all,

I have to create a second baseline (BL2) with updated BL1 Labor units but I want to keep same dates & durations as in BL1.

In short : BL2 Labor units = Budgeted Labor units of the current project and BL2 dates & Durations = same as BL1

Does anyone know how to do this without updating each BL1 Units manually ?

Thanks