I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Tue, 2018-01-02 14:00
Member for
23 years 8 monthsWhat setting (resource and
What setting (resource and cost related fields) is selected on Import template?
Member for
16 years 3 monthsalso check your duration type
also check your duration type make sure it is set to fixed duration & units/time for each activity
Member for
15 years 4 monthsI'm having the same issue.
I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.
Member for
16 years 3 monthsuncheck calculate costs from
uncheck calculate costs from units
Member for
9 years 5 monthsI am having the same issue.
I am having the same issue. I loose the budget units when importing, but not consistently.
About a quarter of the resources maintain their budgeted units.
I am running 17.8 exporting as 8.2 per customer requirements.