Problem in material resource budgeted units after importing xer file

Member for

23 years 8 months

What setting (resource and cost related fields) is selected on Import template?

Member for

16 years 3 months

also check your duration type make sure it is set to fixed duration & units/time for each activity 

Member for

15 years 4 months

I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.

Member for

16 years 3 months

uncheck calculate costs from units 

Member for

9 years 5 months

I am having the same issue. I loose the budget units when importing, but not consistently.

About a quarter of the resources maintain their budgeted units.

I am running 17.8 exporting as 8.2 per customer requirements.