Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Problem in material resource budgeted units after importing xer file

5 replies [Last post]
Yaser A. Al-Bustanji
User offline. Last seen 47 weeks 2 days ago. Offline
Joined: 12 May 2010
Posts: 27
Groups: None

Hi Everyone, 

i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?

unit price is not zero and calculate cost from units is checked

Best regards,

Replies

MK TSE
User offline. Last seen 38 weeks 1 day ago. Offline
Joined: 27 Feb 2002
Posts: 552
Groups: None

What setting (resource and cost related fields) is selected on Import template?

Zoltan Palffy
User offline. Last seen 2 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2428
Groups: None

also check your duration type make sure it is set to fixed duration & units/time for each activity 

Kari Lucas
User offline. Last seen 1 year 31 weeks ago. Offline
Joined: 18 Jun 2010
Posts: 16
Groups: None

I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.

Zoltan Palffy
User offline. Last seen 2 days 4 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2428
Groups: None

uncheck calculate costs from units 

Casey F
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 28 May 2016
Posts: 11
Groups: TILOS
I am having the same issue. I loose the budget units when importing, but not consistently. About a quarter of the resources maintain their budgeted units. I am running 17.8 exporting as 8.2 per customer requirements.