WBS changed after Importing XER file

1 reply [Last post]
haytham saad
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 12 Apr 2013
Posts: 24

i have a situation where after exporting my project and send it to our planning team on project when they try importing the Xer file the WBS is not correct , its all under one level of the WBS what could be the Issue ?

Replies

Zoltan Palffy
User offline. Last seen 6 weeks 8 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

during the importing process modfiy the importing option and for the WBS select insert new