If the durations ratio is by a factor of 8, if normal work day is 8 hours day, perhaps it is due to the difference in how P6 and P3 is storing durations, days versus hour. This is called the planning unit.
If this is so you can solve the issue with global changes but as far as I remember correction for lag values must be manual, the field is not available on the global change.
Google on how to make changes in planning unit for P3, maybe you will hit something of help.
If you opt to keep Days as planning unit you can make the duration changes as per following link.
Member for
14 years 11 monthsHi,May be in your project
Hi,
May be in your project some calendar is wrong,pls check it.
Regards.
Sunil
Member for
16 years 8 monthsjust copy your calender with
just copy your calender with a different name and reassign again.
Take care
Member for
21 years 7 monthsIf the durations ratio is by
If the durations ratio is by a factor of 8, if normal work day is 8 hours day, perhaps it is due to the difference in how P6 and P3 is storing durations, days versus hour. This is called the planning unit.
If this is so you can solve the issue with global changes but as far as I remember correction for lag values must be manual, the field is not available on the global change.
Google on how to make changes in planning unit for P3, maybe you will hit something of help.
If you opt to keep Days as planning unit you can make the duration changes as per following link.
http://www.planningplanet.com/forums/primavera-project-planner-p3/416507/global-changes-samples
Regards,
Rafael
Member for
19 years 10 monthsCheck the
Check the calender.
Regards,
Tariq