everything you mentioned all involve the setting associated with the scheduling option F9 then optons.
Your Scheduling and leveling options may be set and carried over when a project is exported to XER, but they will revert back to default options when imported back to the database when you use the Import option set to Create New, Replace Existing or Add into Existing
The scheduling options for the project are not imported these are machine specific this is why they can differ.
Member for
16 years 3 monthseverything you mentioned all
everything you mentioned all involve the setting associated with the scheduling option F9 then optons.
Your Scheduling and leveling options may be set and carried over when a project is exported to XER, but they will revert back to default options when imported back to the database when you use the Import option set to Create New, Replace Existing or Add into Existing
The scheduling options for the project are not imported these are machine specific this is why they can differ.