Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Remaining early start

2 replies [Last post]
Jean Desjardins
User offline. Last seen 9 years 17 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Hi everyone,

I have an activity that was completed earlier than planned (nov 1st instead of nov 8)

Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)

Is there a way to advance the rem. early start to nov. 1st ?

The only way I found to resolve that is removing the link with the predecessor.

Jean

 

Replies

Jean Desjardins
User offline. Last seen 9 years 17 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Thank you Kylee,

In the schedule options I've checked "Progress override" instead of "Retained logic"

Regards

Kylee Foster
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 10

Hi Jean,

Is there incomplete logic link on the predecessor task?  This will still push the successor task even if the (first) predecessor is finished.  If you've time better to fix this than just deleting the link and it would change the successor task start date.  Careful with interproject links too if that is applicable.

Regards, Kylee.