Hi everyone,
I have an activity that was completed earlier than planned (nov 1st instead of nov 8)
Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)
Is there a way to advance the rem. early start to nov. 1st ?
The only way I found to resolve that is removing the link with the predecessor.
Jean