Start & FInish vs Early Start & Early FInish

I
Irfan Khan 👤 Member for 16 years 10 months
R
Ronald Winter 👤 Member for 23 years 5 months

Have a look at a paper that I co-presented at the 2009 AACE International Conference called " Understanding P6 Dates." I think that that should help answer your question. It is much more complicated that you would imagine.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Irfan,

Early start is the earliest start date where activity starts and early finish is the earliest finish date where activity finishes.

When planner develop the schedule this is the planned date = early date = start date.

Start date is the current date. When activities have start progressing start date become actual date and early start = Remaining Start

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts