Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Early Start/Finish S-curve vs Baseline S-curve

2 replies [Last post]
Cristina Blades
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 27 Aug 2005
Posts: 24
Hi,

I have a new project... all the resources are in, the proposed baseline has now been agreed and am trying to run the required S-Curves: Baseline, Early, Late.

As I have the plan open, and showing Start, Finish, Early Start, Early Finish, Late Start, Late Finish columns, I can see a difference between Start and Late Start, however, there is NO difference in the Start and Early Start dates nor the Finish and Early finish dates. Therefore, I assume that the data for my Early and Baseline S-Curves will be exactly the same.

Any help please?

Thank you,
Cristina

Replies

Rodel Marasigan
User offline. Last seen 18 hours 6 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Christina,
Baseline dates are different from start/ finish date if you have any assigned to current in progress program.
PINAN T.
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102
Without update

Start/Finish date equals Early Dates equals Planned Dates