Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Tracking of Predecessors for change of Remaining Early Start date

1 reply [Last post]
kim jong beom
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 1 Apr 2014
Posts: 5
Groups: None

Dear Planners

 

If one of predecessors is not completed (out of sequence progress) using retained logic, start of successor activity is delayed until all of predecessors are completed. (Remaining early start date is delayed)

It is required to track what activities are not completed. In case of complex project with thousands of activties and lots of relationships, it is very difficult to find which predecessors are not completed.

Is there any solution to find un-completed activities in predecessors easily ?

Simple Filtering of activities are not useful becasue there are so many activities, I just want to filter certain activities linked.

Thank you in advance

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you filter for longest path AND critical path you shoudl be able to get waht you are looking for 

also when you schedule check the log file this wil tell you where you have out of sequence progress