this is way where you don’t have a stop-over to take a nap and have to reach the destination with a basket full of unshattered eggs! safely. I hope you got what i mean!
I suggest we all just ignore Mr Austins ridiculous posts - they obviously dont attempt to add to the sum of planning knowledge, as David says they are from a recruitment consultant not a planner.
Oh how we were all fooled by the once Forensic Claim Analysist, now exposed Recruitment Consultant Chris Austin!
So Chris... do you now understand what the Critical Path is?
As a Recruitment Consultant I doubt you were thinking about the same thing as we planners here - maybe the answer you were looking for was the shortest route to the nearest pub - more your kind of thing eh?
critical path is the longest path connecting the critical activiries of a project fom the staring of that project to the comletion date of the project.
by the way, the critical activities are the activities have total float = zero.
the total float is the difference between the early start and late start and the early finish and the late finish.
RE: What is critical path?
this is way where you don’t have a stop-over to take a nap and have to reach the destination with a basket full of unshattered eggs! safely. I hope you got what i mean!
RE: What is critical path?
In the critical path method we determine some activities that hanve no total & free slack.
RE: What is critical path?
I suggest we all just ignore Mr Austins ridiculous posts - they obviously dont attempt to add to the sum of planning knowledge, as David says they are from a recruitment consultant not a planner.
RE: What is critical path?
Oh how we were all fooled by the once Forensic Claim Analysist, now exposed Recruitment Consultant Chris Austin!
So Chris... do you now understand what the Critical Path is?
As a Recruitment Consultant I doubt you were thinking about the same thing as we planners here - maybe the answer you were looking for was the shortest route to the nearest pub - more your kind of thing eh?
RE: What is critical path?
Thanks ashraf
RE: What is critical path?
critical path is the longest path connecting the critical activiries of a project fom the staring of that project to the comletion date of the project.
by the way, the critical activities are the activities have total float = zero.
the total float is the difference between the early start and late start and the early finish and the late finish.
RE: What is critical path?
give him a break hes only a forensic claims analysis
RE: What is critical path?
refer to the blogg on terminal float you might get an idea of float from that
RE: What is critical path?
Sorry to be ignorant, but what do you mean bby float?
RE: What is critical path?
All activities that have no float defines the critical path