What is critical path?

Member for

21 years 7 months
Permalink

this is way where you don’t have a stop-over to take a nap and have to reach the destination with a basket full of unshattered eggs! safely. I hope you got what i mean!

Member for

22 years 3 months
Permalink

In the critical path method we determine some activities that hanve no total & free slack.

Member for

18 years 7 months
Permalink

I suggest we all just ignore Mr Austin’s ridiculous posts - they obviously don’t attempt to add to the sum of planning knowledge, as David says they are from a recruitment consultant not a planner.

Member for

23 years 6 months
Permalink

Oh how we were all fooled by the once Forensic Claim Analysist, now exposed Recruitment Consultant Chris Austin!

So Chris... do you now understand what the Critical Path is?

As a Recruitment Consultant I doubt you were thinking about the same thing as we planners here - maybe the answer you were looking for was ’the shortest route to the nearest pub’ - more your kind of thing eh?

Member for

19 years 2 months
Permalink

critical path is the longest path connecting the critical activiries of a project fom the staring of that project to the comletion date of the project.

by the way, the critical activities are the activities have total float = zero.

the total float is the difference between the early start and late start and the early finish and the late finish.

Member for

18 years 1 month
Permalink

refer to the blogg on terminal float you might get an idea of float from that