Checking the Calendar against tasks
Forum Sponsor
Top Posters
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
Good luck!
Jamie
Got it. Thanks Alexandre.
Laurie,
Right click on the task bar to open the Properties dialog, select the Task tab, read the Calendar field; use this field to possibly select another calendar.
All the best,
Alexandre