Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Checking the Calendar against tasks

3 replies [Last post]
Laurie Willis
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Hi,

If you have multiple calendars, how can you check which calendar you have previously assigned to a task without adjusting the task length.

Thanks, Laurie

Replies

Jamie Robson
User offline. Last seen 4 years 44 weeks ago. Offline
Joined: 8 Apr 2002
Posts: 3
Another, maybe quicker way to check what calendar has been assigned is to add a column to the spreadsheet table and make it display token>date>calendar. This works fine unless you have more than one calender assigned to the tasks on the bar line.
Good luck!
Jamie
Laurie Willis
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 17 Oct 2006
Posts: 21
Groups: None
Got it. Thanks Alexandre.