PLANNING MANAGER, VinaProjects Ltd. (Vietnam), Construction of the Danang Ocean Villas and Golf Resort Project (Danang, Vietnam)

START Date: 
January, 2010
END Date: 
October, 2011
  • Summarize projects status upstream to senior management, highlighting any unresolved major risks and potential overruns
  • To operate a project controls system in accordance with the planning procedures, providing a consistently high level of service.
  • In charge of pre and post contract construction planning works.
  • Assisting with design and  activities relating to the program
  • Informing projects management on potential impacts of changes
  • Analyze Contractor programmes and report procedures

PLANNING MANAGER, VinaProjects Ltd. (Vietnam), Construction of the Danang Ocean Villas and Golf Resort Project (Danang, Vietnam)

START Date: 
January, 2010
END Date: 
October, 2011
  • Summarize projects status upstream to senior management, highlighting any unresolved major risks and potential overruns
  • To operate a project controls system in accordance with the planning procedures, providing a consistently high level of service.
  • In charge of pre and post contract construction planning works.
  • Assisting with design and  activities relating to the program
  • Informing projects management on potential impacts of changes
  • Analyze Contractor programmes and report procedures

ARUN G

First Name: 
ARUN
Last Name: 
G

Working as a planning manager and using MSP

Professional Since: 
Jul-2009 (14.8 yrs experience)
Oldest experience: 
Jul 2009 (14.8 yrs experience)
Years Experience: 
6

site engineer/assistant planner, tutomaash, wembley car park , wembley stadium

START Date: 
March, 2017

Site Engineer/assistant planner

Setting out position and level  for ground beams and RC slabs.

all general activities about setting out engineering.

Carried out preparation, and the management of construction schedules. primavera p6 EPPM.

Tracked activities and prepared general project reports.

Constructed the Work Breakdown Structure(WBS)

Milestone,Critical Path, Earned value analysis and update as build program.

create and assign Resources, update progress/project. Maintain and Assign baseline.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
0

Peter Williams

First Name: 
Peter
Last Name: 
Williams

A former 'superuser' of MSP that was tasked with converting 120+ live projects to P6 without detriment or hold-up. 100%

Developed a P6 'core' EPC project template for use as a basic schedule that then has 'add-on' discipline templates for the likes of Mechanical, Instrument, Electrical, etc, etc. that creates a consistant, ease-of-use approach for corporate use. 

Professional Since: 
May-1984 (40.0 yrs experience)
Years Experience: 
0

Juanlee Jonker

First Name: 
Juanlee
Last Name: 
Jonker

Setting up WBS

Planning and scheduling lvl 5

Resource planning and management

Monitoring progress on site

EOT claims

KPI's and S-curves

Piping Experience

Mechanical Experience

Structural Experiance

Civil Experience

Electrical Experience

Instrumentation Experience

Shutdown Experience

Professional Since: 
Jan-2011 (13.3 yrs experience)
Years Experience: 
0

amit deshmukh

First Name: 
amit
Last Name: 
deshmukh
  1. Project Planning
  2. Project Scheduling
  3. Cost estimation & control
  4. Project Control
  5. Design Engineering
Professional Since: 
Nov-2011 (12.5 yrs experience)
Years Experience: 
0

James Brown

First Name: 
James
Last Name: 
Brown
Professional Since: 
Oct-2009 (14.6 yrs experience)
Oldest experience: 
Oct 2009 (14.6 yrs experience)
Years Experience: 
46

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content