Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Erection

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

3 years as a Project Engineer, L&T Power Limited, Koradi TPS Expansion Project (3 x660 MW)

START Date: 
December, 2013

Mechanical Projects :- 

  • Involved in Boiler Erection activity including the inspection of boiler pressure parts & boiler structure
  • Coordinating the vendors, contractors
  • Involved in successfull hydotest of boiler
  • Preparing a NCR Report of incomplete activities before hydrotest.

Planning & Monitoring :-

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
150

Planning Engineer, National Petrochemical Company, National Petrochemical Company

START Date: 
June, 2010
END Date: 
May, 2012

 

 

 

Cover Letter

 

Using Primavera Project Planner for enterprise® (P6 ).

 

Experience in software is the leading developer of computer-assisted thinking programs for businesses in the field of project planning, problem solving, and negotiating.

 

Maintenance Planning Engineer (Secondment), The Oman LNG LLC , The Oman LNG LLC

START Date: 
October, 2008

 

¨      Coordinating with the Process, Utility and Workshop departments for day to day planned works and make plan for next day + one month look-ahead activities.

¨      Coordinate with subcontractors in integrating their activites in the master plan.

¨      Planning standby work activities for next day+ one week which can be taken up in case planned works are disrupted due to operational requirements.

Maintenance Engineer, AGORTECH Pvt. Ltd, Construction

START Date: 
January, 2005
END Date: 
April, 2006

Responsible for INSTALLING and MAINTENANCE of the Compressors & Pumps

Provide Preventive Maintenance & Scheduling for preventive and Breakdown Maintenance

Centrifugal Pumps Replacement of mechanical seals, rotor, wearing rings, bearings, shaft alignments and complete overhaul

Reciprocating Pumps Replacement of plungers, plunger packing, valves, inspection and maintenance of crank case and cross head

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content