Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

& Project planning 2)Cost planning 3)Primavera P3 4) Progress Reporting 5) Delay Analising

Senior project manager, Unify, SIP phone

START Date: 
October, 1997
END Date: 
August, 2015

Senior project Manager in the area of telecommunication: developping a SIP phone

planning and controlling ressources, timelines and costs, working on WBS

Director of Project Controls, Dakota Gasification Company, Plant Wide Capital Improvement Projects, Turnaround Schduling

START Date: 
January, 2014

2014 - Present

Dakota Gasification Company

Director of Project Controls -

Experience Hours (Planning & Scheduling): 
3600
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

AGM - Project Management, DLF, NewTown & MyTown - Bangalore projects

START Date: 
December, 2009
  • Project Coordination for the Westend Heights, 19 towers – 1830 apartments (2B+PO+17F), Phase 1 of New Town project. Role of Project Controls Manager. (Work completed and customer handing over started)
  • Site-in-charge for the Bella Greens, 4 & 5 bedroom luxury villa (106 Nos.) project, part of 74 acre New Town integrated township at Begur, Phase 2A, Bangalore.
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
4000
Experience Hours (Forensic Analysis): 
1000

Planning engineer, Construction Kaiser, NIPP, Adeola Odeku Complex

START Date: 
March, 2005
END Date: 
December, 2010
  • Planned the engineering aspect including the design of Inherent safety in the facility project lifecycle, design for installation, commissioning and operation by adopting equipment and specification standards and innovation when appropriate.
  • Planned for procurement activity with subcontractor, execution plan, HSE, QMP, Inspection and Testing.
Experience Hours (Planning & Scheduling): 
9900
Experience Hours (Cost Management): 
3100
Experience Hours (Forensic Analysis): 
2050

3D / 4D Planning Engineer, HACKER INDUSTRIAL LTDA, HYDROPOWER PLANTS

START Date: 
January, 2007

MANUFACTURE OF HYDROPOWER EQUIPMENTS, HYDROTURBINES, ELECTRICAL GENERATORS, ACESSORIES AND MAINTENANCE AND OPERATION SERVICES

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
50

3D / 4D Planning Engineer, HACKER INDUSTRIAL LTDA, HYDROPOWER PLANTS

START Date: 
January, 2007

MANUFACTURE OF HYDROPOWER EQUIPMENTS, HYDROTURBINES, ELECTRICAL GENERATORS, ACESSORIES AND MAINTENANCE AND OPERATION SERVICES

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
50

Engineer - Senior Planning, El Seif Engineering Contracting Co. - Riyadh, Convention Centre, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date: 
October, 2011
END Date: 
February, 2013
Scheduling all EPCM activities using Primavera P6, Summary Reports, Progress ‘S’ Curves, Cash Flow Plans Preparation Internal weekly MIS reports which gives the quantitative progress of Engineering Deliverables, Procurement, Construction progress, Milestone achievement and Critical issues. Two and Four week look ahead programs, Monitoring of works including weekly progress check and analysis, change of internal program as and when required, Periodic
Experience Hours (Planning & Scheduling): 
5700
Experience Hours (Cost Management): 
700
Experience Hours (Forensic Analysis): 
750

Ssubcontrctor Coordinator, Sinclair Oil & Refineries , Chemical Plant Turnarounds (IPL)

START Date: 
January, 2014
END Date: 
November, 2014
Prepare the detailed plans necessary to safely and effectivly execute maintenance work that has been selected, priortized and approved by the gate keeper.  Planning and scheduling in coordination with site scheduler.  Create and maintian task lists for repetitive jobs Outlined detailed work instructioons for work execution, outlining, safety advice, resource, materials, tools and services. Create and maintain Bill Of materials (BOM) and RFI's, Schedule PM tasks to ensure compliances with plan.
Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
100

Ssubcontrctor Coordinator, Sinclair Oil & Refineries , Chemical Plant Turnarounds (IPL)

START Date: 
January, 2014
END Date: 
November, 2014
Prepare the detailed plans necessary to safely and effectivly execute maintenance work that has been selected, priortized and approved by the gate keeper.  Planning and scheduling in coordination with site scheduler.  Create and maintian task lists for repetitive jobs Outlined detailed work instructioons for work execution, outlining, safety advice, resource, materials, tools and services. Create and maintain Bill Of materials (BOM) and RFI's, Schedule PM tasks to ensure compliances with plan.
Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
100

Ssubcontrctor Coordinator, Sinclair Oil & Refineries , Chemical Plant Turnarounds (IPL)

START Date: 
January, 2014
END Date: 
November, 2014
Prepare the detailed plans necessary to safely and effectivly execute maintenance work that has been selected, priortized and approved by the gate keeper.  Planning and scheduling in coordination with site scheduler.  Create and maintian task lists for repetitive jobs Outlined detailed work instructioons for work execution, outlining, safety advice, resource, materials, tools and services. Create and maintain Bill Of materials (BOM) and RFI's, Schedule PM tasks to ensure compliances with plan.
Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
100

Market Place

No results found... (try selecting a different content filter)

Syndicate content