Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

)Planning

4D Planning consultant; Assistant planner, Advanced 3D Technologies, Willis Building, Lime Street, City of London

START Date: 
February, 2005
END Date: 
September, 2006

Pre-construction planning followed by detailed cladding and services planning on two high rise office buildings in Central London. Basis for research project which lead to MSc(Built Environment) and highly commended award for treatise submission on 'Improving construction planning through 4D planning'.

4D Planning consultant; Assistant planner, Advanced 3D Technologies, Soccer City Stadium, Johannesburg, South Africa

START Date: 
January, 2008
END Date: 
September, 2009

Working with the Main Contractor to evaluate the build sequence of sub-contractor program and determine the optimum logistical arrangement for the erection of complicated steel roof structure and cladding material to the roof and facades. Reviewing the build progress and end dates for sectional completion of external works relevant to final handover as well as producing progress reports.

4D Planner, Advanced 3D Technologies, Queensland State Archives; Norwegian Queen and Silver;

START Date: 
May, 2006
END Date: 
December, 2007

Worked in conjunction with Senior planners on a number of governmental and commercial office projects as well as boat fit-out project. Worked with Laing O'Rourke on Queensland State Archives project used as basis for Australian Government guidelines for BIM and 4D Planning.

4D Planning consultant and cladding sub-contractor detailed planning, Advanced 3D Technologies, Paternoster Square, London

START Date: 
September, 2002
END Date: 
March, 2003

Assisted the senior planner in expanded cladding and external works programmes for 3 simultaneous office build projects (each of differing design).

4D Planner and Client pre-construction planning, Advanced 3D Technologies, Mid-Town and Minto Gardens, Toronto

START Date: 
March, 2003
END Date: 
October, 2004

Two High Rise projects with varying roles from Pre-construction planning of the project aligned to cash-flow forecasts as well as daily site planning and monitoring of progress to achieve escalated delivery dates. Fit-out programme extended to nearly 100000 tasks managed using an online monitoring system with hand held devices.

4D Planner, Advanced 3D Technologies, Otago Stadium

START Date: 
August, 2009
END Date: 
December, 2010

Working with site planning team to produce master schedule for review milestone dates and work through detailed erection sequence for the roofing and cladding of the complex enclosed structure.

4D Planning consultant; Assistant planner, Advanced 3D Technologies, Medupi Power Station

START Date: 
September, 2007
END Date: 
November, 2009

Produced bid plan and model in conjunction with M&R project members. Created initial pre-construction model for initial planning review from bid model and then assisted the lead planner in producing expanded levels of programme for use in the daily work schedules. Reworked durations and logic, running scenarios and monitoring progress including progress reporting and client coordination.

Senior Project Controls Engineer, Engineering Consultants Group (ECG), Al Waab City Development

START Date: 
August, 2007
END Date: 
February, 2009

Responsibility includes: Review of contract documents Under the Terms and Conditions of New Contract Format NEC3, Review, comment and approve all baseline schedules, check the s-curves, associated cash flow, resource and cost loading, Preparation of Earned Value report to evaluate project progress, Establishing accurate, regular and timely reports detailing project’s performance and progress such as productivity analysis, resource allocation and cost reports, Review, comment and approve monthly updated schedules, construction method statements, construction sequenc

Senior Project Controls Engineer, Degremont, DOHA WEST sewage treatment works extension No.3

START Date: 
March, 2009
END Date: 
March, 2010

The design-build contract for Doha West is worth USD 180 million and the plant operation contract totals USD 80 million, for a total amount of USD 260 million, awarded by the Public Works Authority in 2006.This is a 135,000 m3/day wastewater facility, the first in the Middle East to use tertiary treatment with ultra filtration membranes. All the treated water will be used for farm irrigation after the commissioning late 2008.

Bid/Project Planning Engineer, Real Estate Development & Investment Company (REDICO KSA), undefined

START Date: 
April, 2005

Specific Achievement:

  • Preparing, Revising P6 Contract Baseline Schedule & Bi-weekly P6 construction updates
  • Monitoring the site implementation of the approved contract schedule and tracking earned value & actual value in terms of cost.
  • Daily, weekly & monthly progress reporting.
  • Preparation of claims for entitlement cost and schedule impact as per signed contract documents.
  • Preparation of two weeks looks ahead schedule and time impact analysis (TIA) for claims.

Preparing and responding correspo

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content