Deputy Construction Manager, Bahria Town Pvt. Ltd., Residential and Infrastructure Developments

START Date: 
September, 2021
END Date: 
November, 2022
 Resource utilization and resource optimization. Execution and construction of Road works with allied services. Creating benchmark relating to budget. Control and monitoring look ahead work schedules. Monitoring and Inspection of quality and daily work progress of contractors. Submission of weekly and monthly progress reports to the seniors. Consultation and coordination with concerned department regarding design and execution related issues including the development and approval of Shop drawings, hig

PLANNING ENGINEER, Habib Rafiq (Pvt.) Ltd., Infrastructure and Building

START Date: 
January, 2018
END Date: 
September, 2021
-Prepare Project Planning Package Comprising of Master Schedule, Progress S-Curves, Resource Histograms, Cashflow Histograms and Procurement Plan.-Verify Work Packages, Work Break Down Structures (WBS), Activities and Codes as per project phase.-Control and monitoring look ahead Work Schedules.-Update Project Schedules on daily / weekly basis. -Submission of daily, weekly and monthly reports to the seniors and client.-Perform daily inspection & test material to achieve quality of construction required in the d

faisal shafiq

First Name: 
faisal
Last Name: 
shafiq
Professional Since: 
Jun-2010 (13.8 yrs experience)
Oldest experience: 
Jul 2010 (13.7 yrs experience, WARNING: 0.1 years variance with Professional Since)
Years Experience: 
12

Civil Site Engineer, Areaa Costruction, Construction of 3 Floors Hospital,Bahria Town, Islamabad, Pakistan

START Date: 
April, 2007
END Date: 
March, 2009

Site Engineer :

Construction of 3 Floors Hospital, Islamabad, Pakistan

 

Jr. Site Engineer, Techno Engineering Services, White Oil Pipeline Project (WOPP) (865 Kilometers Cross-country Pipeline)

START Date: 
January, 2001
END Date: 
December, 2004

Worked as Site Engineer - Trainee with Techno Engineering Service Pvt. Ltd on WOPP - White Oil Pipeline Project.

Jr. Site Engineer, Maxitek, Telecommunication towers

START Date: 
January, 2005
END Date: 
November, 2010
Site Coordinator for Maxitek Engineering Services on telecom EPC projects.

Shuja Ali

First Name: 
Shuja
Last Name: 
Ali

www.ipeccconsultants.com

IPECC Consultants is a project management, systems and technology Solution Company.

Professional Since: 
Nov-2001 (22.4 yrs experience)
Oldest experience: 
Jun 2007 (16.8 yrs experience, WARNING: 5.6 years variance with Professional Since)
Years Experience: 
14

Planning Engineer , NES Pak , IIUI Admin Buildings

START Date: 
January, 2010
END Date: 
January, 2012

Planning Engineer at National Engineering Services Pakistan 

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
100

Farhan Ahmed Memon

First Name: 
Farhan Ahmed
Last Name: 
Memon

 

There are some skills as listed bellow, 

1. Project Planning,

2. Scheduling,

3. Control,

4. Cost Control,

Professional Since: 
Jan-2010 (14.2 yrs experience)
Oldest experience: 
Jan 2010 (14.2 yrs experience)
Years Experience: 
51

Planning Engineer, Pipelink Construction Private Limited (PCL), 1132/ KPD PC-1 installation/Supply of flow lines & Gas gathering Facility.,Sawan North Horizontal-1 Well head Development project – Installation of Well Head Cooler Control/Solar Panel, Sou

START Date: 
January, 2013
END Date: 
October, 2016
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l
Experience Hours (Planning & Scheduling): 
8550
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
50

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.