Planning Engineer, Volker Fitzpatrick, Multi-functional Framework

START Date: 
December, 2014

·         Managing Primavera P6 related planning at a high level containing all agreed activities, deliverables, milestones, client deliverables and all based on Work Breakdown Structure (WBS).

·         Dedicated planning role to assist the site Technicians and Project Manager on site and works with the Area Directors to ensure maximum efficiency, safety and quality on live projects.

Experience Hours (Planning & Scheduling): 
2800
Experience Hours (Cost Management): 
2800
Experience Hours (Forensic Analysis): 
1800

Ken Sheard

First Name: 
Ken
Last Name: 
Sheard
Professional Since: 
Jul-1989 (34.8 yrs experience)
Years Experience: 
0

Planning Manager, Lend Lease, East Village Retrofit Programme

START Date: 
February, 2015

Planning manager to the East Village retrofit accommodation programme to return the Olympic Athletes accommodation back to the public domain.  The site comprises of 2800 accommodation units which are a mixture of market properties, shared ownership and social accommodation units.  Leading a team of 6 planners in the delivery of programme, project control and planning services.  Reporting internally direct to the Head of Programme Delivery and indirectly to the Olympic Delivery Authority. 

Experience Hours (Planning & Scheduling): 
900

Howard Abercrombie-Smith

First Name: 
Howard
Last Name: 
Abercrombie-Smith

Howard is a Senior Contracts Control / Forensic Claims Manager / Project Planner with the last 22 years spent in high profile, complex environments.

Professional Since: 
Sep-1996 (27.7 yrs experience)
Years Experience: 
0

Project Manager, J. LAING CONSTRUCTION ( EASTERN), Multi-Storey building structure

START Date: 
January, 1987
END Date: 
December, 1989

Employed as a Project Manager on £12M Multi-Storey building structure in Southend, Essex.

Experience Hours (Planning & Scheduling): 
4000

Senior Project Planner & Design & Project Co-ordinator (Site Based), Costain Construction, Various

START Date: 
August, 1989
END Date: 
July, 1993

£15M Critall window factory and head office, Braintree, Essex

£20M Head Office for Marconi, Chelmsford, Essex

£14M Shopping Centre, Chelmsford, Essex

£4 BHS Store Fit Out at Lakeside Shopping Centre, Dartford, Kent

Experience Hours (Planning & Scheduling): 
7250

Senior Planner, Mott MacDonald, Essex Waste MBT

START Date: 
December, 2013
END Date: 
January, 2014

Project Description

New build Mechanical & Biological Treatment (MBT) plant to process circa 500k tonnes of household waste in Essex, UK.

 

Role and Responsibilities

Experience Hours (Planning & Scheduling): 
300

Andrew Langridge

First Name: 
Andrew
Last Name: 
Langridge

I have over 2 decades of experience working with Government and Industry to improve their capability to generate robust results for cost forecasting, estimation, cost modelling and project controls, these activities are a foundation stone for any organisation who aim to capture and deliver profitable projects and products.

Professional Since: 
Jan-1990 (34.3 yrs experience)
Years Experience: 
0
Guild Accreditation: 
Awaiting Applicant
GPC Member Since: 
Sun, 2014-05-25 (All day)

Tim Neobard

First Name: 
Tim
Last Name: 
Neobard
Professional Since: 
Jun-2006 (17.9 yrs experience)
Oldest experience: 
Sep 2009 (14.7 yrs experience, WARNING: 3.3 years variance with Professional Since)
Years Experience: 
4

kirk culley

First Name: 
kirk
Last Name: 
culley
Professional Since: 
Mar-1996 (28.2 yrs experience)
Oldest experience: 
Jan 1995 (29.3 yrs experience, WARNING: 1.2 years variance with Professional Since)
Years Experience: 
43