Kusile Coal Fired Power Station – South Africa

Senior Project Planner - (Unit 1 & Unit 2), Murray & Roberts, Kusile Coal Fired Power Station – South Africa

START Date: 
August, 2015
END Date: 
February, 2017

• Supervised the Master Program Schedule maintenance including input, revision and updating.

Experience Hours (Planning & Scheduling): 
3350
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
100

Project Cost Analyst, Pragmatis, Kusile Coal Fired Power Station – South Africa

START Date: 
July, 2015
  • Weekly FPMS reports
  • Monthly Expenditure flows
Experience Hours (Planning & Scheduling): 
50
Experience Hours (Cost Management): 
150

Senior Planner, Bateman Engineering Projects RSA, Kusile Coal Fired Power Station – South Africa

START Date: 
November, 2006
END Date: 
March, 2011

At Bateman Enginered Technologies BET, when I left the company is was occupying the position of Senior Planner manager responsible for managing the team of planners.

My responsibilities included:

  • Team Management and evaluation,
  • Setup and execution of project programmes,
  • Monitoring, controling and Reporting

Some of the project programme I setup include:

Experience Hours (Planning & Scheduling): 
7650
Experience Hours (Cost Management): 
1200

Senior Planner, Bateman Engineering Projects RSA, Kusile Coal Fired Power Station – South Africa

START Date: 
November, 2006
END Date: 
March, 2011

At Bateman Enginered Technologies BET, when I left the company is was occupying the position of Senior Planner manager responsible for managing the team of planners.

My responsibilities included:

  • Team Management and evaluation,
  • Setup and execution of project programmes,
  • Monitoring, controling and Reporting

Some of the project programme I setup include:

Experience Hours (Planning & Scheduling): 
7650
Experience Hours (Cost Management): 
1200

Senior Planner, Bateman Engineering Projects RSA, Kusile Coal Fired Power Station – South Africa

START Date: 
November, 2006
END Date: 
March, 2011

At Bateman Enginered Technologies BET, when I left the company is was occupying the position of Senior Planner manager responsible for managing the team of planners.

My responsibilities included:

  • Team Management and evaluation,
  • Setup and execution of project programmes,
  • Monitoring, controling and Reporting

Some of the project programme I setup include:

Experience Hours (Planning & Scheduling): 
7650
Experience Hours (Cost Management): 
1200

Senior Planner, Bateman, SNC-Lavalin, Evra Consulting, Kusile Coal Fired Power Station – South Africa

START Date: 
June, 2016

I currently perform the role of a Senior Planning Consultant for a specilist project Planning consultancy called Evra Consulting.

I occupy a role which involves business development and plannig supervison. 

EVRA COnsultancy offers planning services primariliy in the Construction, Power and Infrastructure. Inaddidtion to this the firm specializes in Forensic Planning services. 

Experience Hours (Planning & Scheduling): 
6600

project planner, ESKOM, Kusile Coal Fired Power Station – South Africa

START Date: 
June, 2012
END Date: 
February, 2016
Using the programme for construction progress monitoring, identifying potential problems, identifying the critical activities, near critical activities and working with the contractor to close deviations..  Preparing and maintaining construction schedules including development of critical path, project float and building as built schedules having taken into consideration all delays experienced.
Experience Hours (Planning & Scheduling): 
7100
Experience Hours (Cost Management): 
2000

Senior Planner, Bateman Africa, Kusile Coal Fired Power Station – South Africa

START Date: 
April, 2011

Employed as Lead EPC Planner overseeing three major packages (projects) on the Eskom Kusile Power Station. (LSTK Project)

Implementing project control system, including POP (Procurement Operating Plan) & EOP (Expediting Operating Plan).

Developing the EPC Schedule to provide an object orientated WBS, on a fully resource and cost loaded schedule. Progress performance and analysis reporting, including, S-curves and progress reports. Supervise, manage & mentor two Planners working under me.