Senior Planner, Bateman Engineering Projects RSA, Kusile Coal Fired Power Station – South Africa

START Date: 
November, 2006
END Date: 
March, 2011

At Bateman Enginered Technologies BET, when I left the company is was occupying the position of Senior Planner manager responsible for managing the team of planners.

My responsibilities included:

  • Team Management and evaluation,
  • Setup and execution of project programmes,
  • Monitoring, controling and Reporting

Some of the project programme I setup include:

  • Thickeners,
  • Floatation Cells,
  • Conveyors,
  • Load Cells,
  • Electrostatic Precipitators,
  • Dust Extraction

Some of the projects I workde on include:

  • Kusile Power Station Materials Handling packages. This included the Terrace area, Conveyors & Machines - R1.2Biillion, Stockyard, Conveyors & Machines R1.1Billion and the Limestone, Conveyors & machines - R300mil.
  • Klipspruit Coal Mine Bulk Materials Handling
  • Rossing Uranium Dust Extraction
  • Impala Platinum Electrostatic Precipitator
  •  
Experience Hours (Planning & Scheduling): 
7650
Experience Hours (Cost Management): 
1200