Interconnection of Gas Transport Systems from Mid-Eastern to Western Venezuela (ICO) Phase II

Site Lead Planner, TIVENCA, Interconnection of Gas Transport Systems from Mid-Eastern to Western Venezuela (ICO) Phase II

START Date: 
February, 2008
END Date: 
May, 2009

Planning and Control Engineer for Quality Assurance and Quality Control of the Interconnection of Gas Transport Systems from Mid-Eastern to Western Venezuela (ICO) Phase II (EPCC Project) Project with a key role in the development and management of a monitoring program for measurement the efficiency and efficacy  of the project. The main responsibilities included:

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
50