Primavera Software:My comapny has given a training in Primavera Software.We can create a Unlimited baseline in Primavera.I worked in 2X685 MW Super critical Power Plant.Every Month Contractor is sending the Primavera File to us.I am uplloading the document in Primavera and assigning the Baseline to it and then i will update Schedule and Tracking the schedule ,identifying the Critical path
MS Project:It is the Basic tool before learning the Primavera.In my project Package(WTP, RWI,CHP,AHP ) vendors submitting schedule through MSP only.So every month i am updating the small