Planning Manager

Planning Manager, Multiplex, Preconstruction

START Date: 
December, 2019
END Date: 
June, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Planning Manager, Multiplex, Preconstruction

START Date: 
December, 2019
END Date: 
June, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Planning Manager, Multiplex, Multiple

START Date: 
December, 2019
END Date: 
June, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Planning Manager, Multiplex, Multiple

START Date: 
December, 2019
END Date: 
June, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Planning Manager, Multiplex, Multiple

START Date: 
December, 2019
END Date: 
June, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Planning Manager, Multiplex, Multiple

START Date: 
July, 2020

Tender Planning 

In my short time at multiplex I have worked on two significant tenders including the fit out of the new HQ for a large tech company in the Battersea power station as well as £350m residential development in Canary Wharf. Unfortunately, because of covid- 19 and the effect on the portfolio of work undertaken by Multiplex I was included in their redundacies.  

Experience Hours (Planning & Scheduling): 
950

Technician, Technology director, Planning manager, China Railway First Group Co; Ltd, Shenyan railwayYulin station project; Yuhuai railway Chongqing jiangbei station project; Datang Chaozhou 2*600MW plant.

START Date: 
July, 2000
END Date: 
July, 2005
  1. Be responsible in technique in the project.
  2. Establish the technique management rules, training the elementary engineering.
  3. Work out the project construction management plan & the special project construction scheme.
  4. Organize & take part in the reviewing of drawing, technical disclosure.
  5. Check out the condition at the beginning of construction, work out the report on starting construction.
  6. Effectively control the work progress, solve the technical matter on site.
  7. Coordinate with quality, safety, schedule, cost in the project, be su
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
10000

Planning Manager, Highbar Technocrat, Pune Metro Rail Project

START Date: 
June, 2018

Creating Master Program for Metro with identifying the weightages, Monitoring the progress of all Contracts. 

Linking the 3D model with Primavera Schedule and Cost from SAP.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
600

Planning Manager , Mace, One Crown Place

START Date: 
March, 2019

Mace Major Projects

Market Place