Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline from another File or Excel

1 reply [Last post]
Vasat Tore
User offline. Last seen 7 weeks 5 days ago. Offline
Joined: 24 Mar 2007
Posts: 3
Groups: None

Hi everyone,

 

I have 2 TILOS files and I want to set one of them as baseline to the other.

What is the best way to do this?

 

Thanks

Replies

Alexandre Faulx-B...
User offline. Last seen 11 hours 24 min ago. Offline
Joined: 20 Jan 2003
Posts: 1336

Hi Vasat,

I hoped that somebody had the solution, but I was wrong. I have found nowhere in Tilos the way to copy the schedule of one project to make it the baselin of another one, as it is possible in Primavera or Asta Powerproject

When you baseline a project, my experience is that you can only select activities in the current project.

Did you ask the question to Tilos people?

All the best,

Alexandre