Copy a bundle of activity from one file another file

3 replies [Last post]
Izam Zakaria
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Guys,

What is the best way to copy a bundle of activities from one project to another project?? Is it by copying the WBS from one file to another file is the best practice for Primavera 6?

or export to excel then further import to new file (incl. pred and succ)?

Thanks for your direction sooner

Replies

Rodel Marasigan
User offline. Last seen 1 day 10 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
If you are using activity codes then it will also copied if activity code is also tick or selected to copy but you need to define activity code on the other projects if not global. You can use Activity Window but group and sort by EPS/WBS or WBS otherwise it won’t allow you to copy.
Izam Zakaria
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Rodel,

What happen if I’m using activity codes. Do I still have any chances?
Rodel Marasigan
User offline. Last seen 1 day 10 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Izam,
Copy from WBS window is the fastest way and best approach. You can include links within WBS copied or including external links if needed.