Vladimir,
strict links were mentioned in this topic, but I found a couple of other things about them, which I don't understand.
1) In the below example link between Activity2 and Activity4 is Strict. When the project resource leveled the following issues are observed:
a) The strict link is not respected even thought it can be respected, if Activity 2 is delayed
b) There is no warning, that strict link is not respected
![photo StrictLinksProb1_zps3fbc7c09.png](http://i1307.photobucket.com/albums/s592/ev2geny/StrictLinksProb1_zps3fbc7c09.png)
https://drive.google.com/file/d/0B1FBt_G3gCVqMHJITEJmcUxNVWc/edit?usp=sharing
2) In the 2nd example a link between activity 2 and activity 3 is strict. When the schedule is resource leveled the following issues issue is observed
a) Schedule is by far not optimal. There is no need to delay Activity 2 to start after Activity 5
![photo StrictLinksProb2_zpsf35f4636.png](http://i1307.photobucket.com/albums/s592/ev2geny/StrictLinksProb2_zpsf35f4636.png)
https://drive.google.com/file/d/0B1FBt_G3gCVqXzNUaXhzZDVhNDA/edit?usp=sharing
Regards.
Evgeny
Replies