start, finish and total float float

2 replies [Last post]
Md Sakib Islam
User offline. Last seen 7 years 40 weeks ago. Offline
Joined: 22 Aug 2015
Posts: 7

Greetings to All.

(it might be a stupid question)

In P6 project layout we use start, finish and total float columns. we have original duration too. My question is on what basis total float is calculated. because total float = late start- Early start or late start - early start

and we dont enter any kind of early or late start or finsh shedule, but still total float is provided. how is it possible. 

(Thanks in Advance)

Replies

Rafael Davila
User offline. Last seen 1 hour 19 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

You enter project start, activity durations and logic, after schedule run early and late dates are calculated during forward and backward calculations then float values are calculated and all can be shown on the same table.

Mike Testro
User offline. Last seen 1 week 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi MD

Latest start is where all the float is used up.

Best regards

Mike T.