Greetings to All.
(it might be a stupid question)
In P6 project layout we use start, finish and total float columns. we have original duration too. My question is on what basis total float is calculated. because total float = late start- Early start or late start - early start
and we dont enter any kind of early or late start or finsh shedule, but still total float is provided. how is it possible.
(Thanks in Advance)