A quick question on Duration versus units/time

1 reply [Last post]
Scottie Bell
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 25 Apr 2011
Posts: 6
Groups: None

Hi there. My question is, is there a way to keep my units/time from changing in my resources when i change my original duration. It is frustrating me because i cant figure it out, and am manually having to go back and re adjust my units/time. I thought the answer would be in the duration settings, but i dont know. Is there a way to do it?

Thank you!

Scottie Bell

Replies

Scottie Bell
User offline. Last seen 7 years 22 weeks ago. Offline
Joined: 25 Apr 2011
Posts: 6
Groups: None

I figured it out-

I changed the duration type from fixed duration & units to fixed duration and units/time. Works great if anyone has the same issue. If your duration type is not set to the correct setting from the start, you will need to go to each individual activity your changing the original duration for, and change duration type in the general tab.

Have a great day!