Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Theoric Duration % complete

2 replies [Last post]
Marcel Frances
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 10 Jul 2012
Posts: 15
Groups: None

Hi all

Since months ago I have this issue in mind but I did not discover this site till yesterday. It seems there are a lot of pundits here so sure my question will get solved. Here I go.

Let's say that I have an activity in both in the project and in the baseline. This activity was planned to start in the past but it has not started. Hence, the physical % completion is obviously 0. How can I see though the theoric Duration % Complete based on the dates in the baseline?

Thanks in advance,

Frances.

Replies

Marcel Frances
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 10 Jul 2012
Posts: 15
Groups: None

Thanks for your answer Alexander.