CPI Problem

No replies
ravirg gehlot
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 22 Sep 2011
Posts: 29
Groups: None

Hi

 

I am facing a problem to calculate CPI for my project ...Project have 3000 Engineering activities

but I have 3 datas only

Project management budget - which is not in my schedule

Support activities -  which is not in my schedule

Engineering Budget - I have in the scheule

 

If I calculate CPI from % complete of schedule like - BCWP/AC .....

Then This will give me wrong CPI because there is no activity like project managent & suppot serivce in my schedule ...

Now can any one tell me How I can resolve this problem