Hi
I am facing a problem to calculate CPI for my project ...Project have 3000 Engineering activities
but I have 3 datas only
Project management budget - which is not in my schedule
Support activities - which is not in my schedule
Engineering Budget - I have in the scheule
If I calculate CPI from % complete of schedule like - BCWP/AC .....
Then This will give me wrong CPI because there is no activity like project managent & suppot serivce in my schedule ...
Now can any one tell me How I can resolve this problem