resource spreading

1 reply [Last post]
Anthony Peters
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 5 Apr 2007
Posts: 18
Groups: None

Alright guys,

I split my resources (GBP) in my program into periods that i have set up in the financial period data. I have ended the year on 31/03/2012. I have got activities with costs assigned with the finish date on the 3rd March ( planned finish date is 5th March), however when i look at the resource assignment spreadsheet it is carrying over a proportion of the monies into next year. Does anyone know why this is happening? I know how to reset it - i delete the resource and recreate it. Im just wondering how it happens as the finish date is nowhere near the end of the yeat.

Replies

Mike Testro
User offline. Last seen 34 weeks 6 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Anthony

Sometimes there is an offset period between the date the cost is incurred and the date of payment.

Check your settings to see if this is the problem.

Best regards

Mike Testro