P 6 Constraints not being honored

3 replies [Last post]
John Truelove
User offline. Last seen 14 years 1 week ago. Offline
Joined: 2 Feb 2010
Posts: 3

We have a number of projects which are update once a week re scheduled and levelled and for months applied Constraint dates have been honored but in the last few weeks these constriants are not working unless they are Mandatory Constraints.  I suspect someone has updated a global setting but cannot find find it.  Can anyone advise

 

Regards John.

Replies

Amit Parmar (PMP)
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 12 Nov 2010
Posts: 94
Groups: None

Hi John,

What type of constraints are you using? Only mandatory constraint fixes the date of the activity and other constraints affect the float of the activity. Please read the following posts on constraints for a better clarity on how constraints behave http://www.primaverablog.in/category/important-topics/constraints/ .

If you can give me more details about the type of constraint, Start, Finish dates etc. then we can discuss further.

Thanks & Regards

Amit

Check out my blog on Primavera at http://www.primaverablog.in

Mark Greenhalgh
User offline. Last seen 13 years 38 weeks ago. Offline
Joined: 21 Jul 2003
Posts: 13

Keep constraints to a minimum.  Use them only for contractual required dates when there would be a penalty for not hitting the date.  Have you tried Longest Path Approximator?  http://scheduling.spacetechnology.net  It is capable of moving the data date back to the beginning of the month, and then you can see the critical path.  Hint:  Ask for  a free sample!

Dieter Wambach
User offline. Last seen 8 years 14 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

John

If you use constraints there can be a conflict between relationships and constraints, e.g. an activity is delayed, and due to sequences and durations other activities' constraints can't be fulfilled. Mandatory constraints win, the others loose against the relationships and the activities will be delayed.

Check the log file of scheduling (F9). At the bottom you can find those conflicts.

Do you really need those constraints?

Hope this helps

Dieter