Can we remove assigned constraints in Project?

3 replies [Last post]
Ritesh Kumar
User offline. Last seen 1 year 42 weeks ago. Offline
Joined: 9 Apr 2006
Posts: 49
Dear all
In P3e, Can we remove assigned constraints in Project?

Regards
Ritesh Kumar


Replies

Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
... choose none.
Tu Huynh Van
User offline. Last seen 15 years 4 weeks ago. Offline
Joined: 8 Aug 2006
Posts: 21
yeah, im sure u can, step as folow:
1. select activity that u want to remove constraints
2. In Activity Detail, select status tab
3. Remove all constraints by choiced none in "constraints box"

best of luck

Khuong Do
User offline. Last seen 16 years 32 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 38
Groups: None
Surely you can.
_ Choose the activity
_ Click on Status tab of Activity Detail
_ In Constrain section, click the dropdown list and choose