How to consider miscellaneous costs, and resources
Forum Sponsor
Top Posters
Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Thanks Rodel so much, this subject was my headache for a long time, but now, no more.
Thanks Shareef for rising this subject.
Duy
Thanx Rodel
Now I understand!!!
Shareef,

If the resource is under WBS summary activities or Level of effort activities, you can change the planned date of each resource so the distribution of cost will be based on the estimated planned date. If the activities are sitting at one WBS then use WBS summary activities otherwise use LOE (same as hammock) and link the first activity SS and last Activity FF and assign resource. See sample below:
Thanx once again Rodel,
You are the P6 user manual for a lot of planners...
Now I would like you to detail your reply
LOE activities are Level of Effort I guess. Is it similar to hammock activity?
"You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource".
can you clarify the above a little more in detail?
( WBS summary activities???.... change planned date for each resource???)
Hope youll have the patience!!!
Thank you once again Rodel
Shareef,
You can use LOE activities and assigned expenses, misc materials, sundries...etc...where applicable if you dont have designated activities for those item. You can also use WBS summary activities (i.e. Construction) for those items and you can specifically change planned date for each resource.