Hello
I would like to know how to incorporate miscellaneous costs, labour, plant & materials for activities.
Normally when resources are entered only the major resources come to mind but when actually executed based on the site conditions the resources required may increase and some times additional materials which were not though of such as extra binding wire for steel fixing, plastic sheets for blinding, solitex boards for joints,....
There would actually be a whole list of minor materials and sometimes transportation charges from store to site or within site; then may be cost of water tank for watering, cost of water.
P6 is well built for costing.
Now how do we handle this???
Previously I have worked on costing of a project and the costing was done using an ERP package called BAAN.Here we used to have an item called sundries or micellaneous.
Is it something like this?
Regards
Shareef A Azeez
Replies