How to group and sort for a single resource ID into multiple criteria in resources usage profile

1 reply [Last post]
Galav Dani
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 6 Aug 2014
Posts: 4
Groups: None

Hello experts...

Imagine there is a resource defined as “Fitter” and I had allocated that resource in many activities in schedule. 

Now my schedule comprises of different units called as unit A, B, C Etc… 

Now during resource usage profile how can I show unit wise amount of over allocation of “Fitter” ?

What method should i use?

Replies

Raymund de Laza
User offline. Last seen 48 weeks 1 day ago. Offline
Joined: 23 Nov 2009
Posts: 762
Hi...Set a Max Unit / time for the Resource.