Hello I am having a nightmare with costs on Primavera
I have entered some resources against activities
Activity 1 = 10 days - Resource = Labour cost = £1000
Activity 2 = 10 days - Resource = Plant cost = £1000
Both activities are scheduled to happen in the future, I have now worked out that the tasks will actually take 15 days now but the cost will remain the same. So when I change the duration the budgeted cost just drops out completely? What do I need to do to make sure the cost stays where it is and doesnt change unless I manually change it or there is a proper method behind the change in figure ie I could understand if the figure went to £1500 for example but to just be erased is madness?
I assume there is a tick box somewhere that I can adjust to make sure this stops happening?
Please help me!!
Replies