Remaining float in P6

4 replies [Last post]
Shah. HB
User offline. Last seen 20 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

What is remaining float ? How it is computed?

Replies

Shah. HB
User offline. Last seen 20 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many thanks for sharing your article Mr.Ronald
Ronald Winter
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
I co-published a paper titled, "Understanding P6 Dates" that explains Remaining Float. The secret is that Remaining Float is different from Total Flaot is you are using resource leveling. I hope that this helps!
Shah. HB
User offline. Last seen 20 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many Thanks Rodel
Rodel Marasigan
User offline. Last seen 16 hours 53 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Shahul,
My understanding with remaining float is the same as total float and they computed the same. Once the activity is in progress the remaining early date = early date and when finished or completed remaining early date = null and early date = data date.