Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Show impact of planned vs actual resource

2 replies [Last post]
Paul Garland
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 30 Dec 2005
Posts: 10
Groups: None
All

I’m trying to demonstrate the impact of a reduced resource on the planned duration of an activity.
The scenario is: an activity was planned to take say 10 hours using 10 men on site (100 man hours) This is the baseline planned duration. In the actual circumstances, only 5 men were allowed on site, so the work takes 20 hours. I want to show this not only in the gantt chart, thus demonstrating the cumulative affect on successor activities, again with less than planned resources but also in the resource histogram. I want to show a resource distribution with the planned and actual either side by side or in total as a stacked bar chart.

Any suggestions?

Paul

Replies

Paul Garland
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 30 Dec 2005
Posts: 10
Groups: None
Thanks

Paul
Rodel Marasigan
User offline. Last seen 3 days 2 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Paul,
That is easy. Create your baseline first using the 100hrs for 10 men. Use fixed/unit duration type so when adjusting time/unit it will automatically adjust the duration).
Then Maintain baseline and assigned as Project Baseline.
Adjust the schedule using 5men for 100hrs. See sample below:
Resource Impact