Impact Of Calc Start-To-Start Lag From Actual Start

4 replies [Last post]
Olubukola Fasoyin
User offline. Last seen 11 years 19 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 27
Hi Guys,

In P6 there are 2 options in calculating start to start Lag for progressed activities. And this may give different project finish or key milestone dates.

What is best practice. should either of these options be rejected as a client or be contested as a contractor.

Cheers

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Khuong has the correct explaination 

Khuong Do
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None

Hi there,

I wrote an article to explain these options.

Kindly read it here https://doduykhuong.com/2020/01/26/primavera-p6-schedule-options-calculate-start-to-start-lag-from/

Regards,

Khuong

Abdul Khadeer
User offline. Last seen 11 years 41 weeks ago. Offline
Joined: 11 Sep 2004
Posts: 32
Groups: None
Gentleman,

Can you expalin the question and answer as well please.

thanks
AK
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
A lot depends on the project status and also on the agressiveness of the Planning Engr.

I would prefer to have this calculated using Early Start, as this will give more conservative Schedule but again this will also lead to delay in start of successor.

Choice is yours!!