Hi Guys,
In P6 there are 2 options in calculating start to start Lag for progressed activities. And this may give different project finish or key milestone dates.
What is best practice. should either of these options be rejected as a client or be contested as a contractor.
Cheers
In P6 there are 2 options in calculating start to start Lag for progressed activities. And this may give different project finish or key milestone dates.
What is best practice. should either of these options be rejected as a client or be contested as a contractor.
Cheers