Resource: One Supervisor for the full term of a Project

1 reply [Last post]
Ruel Camaquin
User offline. Last seen 3 years 31 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
Guys,

How do i do this, i have foreman for the complete duration of a project, how do i put him in the resources just once? if i put the foreman in every activities that i have, then my resources cost for the foreman shall be overallocated. Kindly give me tips & tricks on how to do this in P6.

Thanks in advanec for your immediated response.

Ruel

Replies

Rodel Marasigan
User offline. Last seen 15 hours 24 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Ruel,
Use Level Of Effort activity link SS to first activity where the foreman assigned and FF to last activity and assign resource foreman. If will automatically adjust if the last activity move forward or backward.