Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Turning a non-resource level schedule into a resource loaded one (P6)

1 reply [Last post]
Eric Gonzalez
User offline. Last seen 20 weeks 2 days ago. Offline
Joined: 30 May 2019
Posts: 14

I have taken over a schedule that is not resource loaded. However, management would like to add resources even though job has already started. The job is a EPC project. The constuction side is resoure loaded but not the engineering side. What would be the best solution for this task? Would I need to make a copy of the baseline, export, make the changes to include resources then import back in? 

Replies

Zoltan Palffy
User offline. Last seen 3 hours 13 min ago. Offline
Joined: 13 Jul 2009
Posts: 2735
Groups: None

add a labor resource 

export both to excel 

copy the non labor data values to the labor resource

import the excel file

deleted the non labor resource 

done