Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Turning a non-resource level schedule into a resource loaded one (P6)

1 reply [Last post]
Eric Gonzalez
User offline. Last seen 2 days 3 hours ago. Offline
Joined: 30 May 2019
Posts: 4

I have taken over a schedule that is not resource loaded. However, management would like to add resources even though job has already started. The job is a EPC project. The constuction side is resoure loaded but not the engineering side. What would be the best solution for this task? Would I need to make a copy of the baseline, export, make the changes to include resources then import back in? 

Replies

Zoltan Palffy
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2335
Groups: None

add a labor resource 

export both to excel 

copy the non labor data values to the labor resource

import the excel file

deleted the non labor resource 

done